Accomplishments
July 2023 - June 2024 (FY 24)
- The NGN program migrated its 100th building
- The NGN program migrated its first Resident Hall over to NGN
- Post-migration surveys are implemented and show positive feedback from the Yale community about the NGN program’s work
- NGN building migrations are being completed faster, reducing impact on community members
July 2022 - June 2023 (FY 23)
- Migrated 24 buildings over to NGN - 95 total
- The NGN program completed the migrations of all Medical Campus buildings
- The NGN wireless team deployed 1,968 access points across the completed Yale Medical Campus
- The NGN wireless team deployed 703 access points as part of the Wireless Upgrade Initiative
- NGN full team, on-site workshops throughout the year, resulting in continuous program improvements
July 2021 - June 2022 (FY 22)
- Migrated 50 buildings over to NGN - 71 total
- The NGN program completed the migrations of of all VA Campus buildings
- The NGN program completed the migrations of all Athletic Field buildings
July 2020 - June 2021 (FY 21)
- Migrated 21 buildings over to NGN
- 25 Science Park transitioned to the NGN wired network
- 205/221 Whitney Avenue pilot building: wired and wireless networks transitioned to NGN core as ITS Production building
- 100 Church Street South pilot building: wired and wireless networks transitioned to NGN core and managed as ITS Production building
July 2019 - June 2020 (FY 20)
- New Cisco core network equipment deployed